Orders 2024

SL No Subject Petition No. & Date of Issue of Order Date of Uploading Type of Order
21 Order Dated 31.12.2024 in respect of Petition No. TP-17 of 2024 for Approval of Capital Cost and Levelised Tariff for Subbung SHP 3 MW, filed by DHPD.
[DOWNLOAD]
TP-17 of 2024
31/12/2024
07/01/2025 Tariff Peition
20 Order Dated 31.12.2024 in respect of Petition No. TP-16 of 2024 for Approval of Capital Cost and Levelised Tariff for Mukto SHP 6 MW, filed by DHPD.
[DOWNLOAD]
TP-16 of 2024
31/12/2024
07/01/2025 Tariff Peition
19 Order Dated 31.12.2024 in respect of Petition No. TP-15 of 2024 for Approval of Capital Cost and Levelised Tariff for Khajalong MHS 1.5 MW, filed by DHPD.
[DOWNLOAD]
TP-15 of 2024
31/12/2024
07/01/2025 Tariff Peition
18 Order Dated 31.12.2024 in respect of Petition No. TP-14 of 2024 for Approval of Capital Cost and Levelised Tariff for Payu MHS at Koloriang 1 MW, filed by DHPD.
[DOWNLOAD]
TP-14 of 2024
31/12/2024
07/01/2025 Tariff Peition
17 Order Dated 31.12.2024 in respect of Petition No. TP-13 of 2024 for Approval of Capital Cost and Levelised Tariff for Nuranang Ph-II SHP 1 MW, filed by DHPD.
[DOWNLOAD]
TP-13 of 2024
31/12/2024
07/01/2025 Tariff Peition
16 Order Dated 31.12.2024 in respect of Petition No. TP-12 of 2024 for Approval of Capital Cost and Levelised Tariff for Angong Nallah MHS 4.5 MW, filed by DHPD.
[DOWNLOAD]
TP-12 of 2024
31/12/2024
07/01/2025 Tariff Peition
15 Order Dated 31.12.2024 in respect of Petition No. TP-11 of 2024 for Approval of Aggregate Revenue Requirement and Tariff Order for FY 2024-25 filed by DHPD.
[DOWNLOAD]
TP-11 of 2024
31/12/2024
07/01/2025 Tariff Peition
14 Order Dated 16.12.2024 in respect of Petition No. TP-08 of 2024 for Approval of Capital Cost and Tariff for Sumbachu SHP 3 MW, Zemithang filed by HPDCAPL.
[DOWNLOAD]
TP-08 of 2024
16/12/2024
16/12/2024 Tariff Peition
13 Order Dated 26.11.2024 in Petition No. MP-09 of 2024 in Respect of Petition for approval of Power Sale Agreement (PSA) between Department of Power, Government of Arunachal Pradesh and M/s Shree Salasar Industries Private Limited.
[DOWNLOAD]
MP-09 of 2024
26/11/2024
26/11/2024 Miscellaneous Peition
12 Order Dated 25.10.2024 in Petition No. MP-08 of 2024 in Respect of Petition for approval of Draft Power Purchase Agreement (PPA) between Department of Power, Government of Arunachal Pradesh and M/s Halaipani Hydro Project Private Limited.
[DOWNLOAD]
MP-08 of 2024
25/10/2024
26/10/2024 Miscellaneous Peition
11 Order Dated 08.10.2024 in Petition No. MP-07 of 2024 in Respect of seeking relaxation of Regulation 3.21.4 (1) read with Annexure 10.10 of Supply Code relating to security deposit for new connection, Aether Alloys LLP vs Department of Power, Arunachal Pradesh & Department of Industries, Government of Arunachal Pradesh.
[DOWNLOAD]
MP-07 of 2024
08/10/2024
09/10/2024 Miscellaneous Peition
10 Order Dated 23.08.2024 in Petition No. TP-09 of 2024 in Respect of Determination of levellised generic tariff for the Small Hydro Projects up to one MW for FY 2024-25 under Regulation 7 of the Arunachal Pradesh State Electricity Regulatory Commission (Terms and Conditions for Determination from Renewable Energy Tariff) Regulations, 2024.
[DOWNLOAD]
TP-09 of 2024
23/08/2024
23/08/2024 Tariff Peition
09 Order Dated 26.07.2024 in Petition No. MP-06 of 2024 in Respect to Seeking relaxation of Regulation 3.21.4(1) read with Annexure 10.10 of Supply Code relating to security deposit for the new connection in interest and for fostering economic development, Aether Alloys LLP.
[DOWNLOAD]
MP-06 of 2024
26/07/2024
26/07/2024 Miscellaneous Peition
08 Application praying for approval of new service connection charges in electrified areas up to a load of 150 KW in compliance of Regulation 3.6.4(10) of APSERC (Electricity Supply Code) Regulations 2024, Department of Power, Government of Arunachal Pradesh.
[DOWNLOAD]
MP-04 of 2024
26/07/2024
26/07/2024 Miscellaneous Peition
07 Order Dated 26.07.2024 in Petition No. TP-03 of 2024 With Respect To AGGREGATE REVENUE REQUIREMENT FOR FY 2024-25 to FY 2026-27AND RETAIL SUPPLY TARIFF ORDER FOR FY 2024-25 For Department of Power, Government of Arunachal Pradesh
[DOWNLOAD]
TP-03 of 2024
26/07/2024
26/07/2024 Tariff Peition
06 Petition for approval of the Power Purchase Agreement between Department of Power, Government of Arunachal Pradesh and M/s Kangteng Hydro Power Pvt. Ltd.
[DOWNLOAD]
MP-03 of 2024
12/06/2024
12/06/2024 Miscellaneous Peition
05 Petition for first amendment of PPA between M/s Devi Energies Pvt. Ltd. and Department of Power, Government of Arunachal Pradesh
[DOWNLOAD]
MP-02 of 2024
13/06/2024
13/06/2024 Miscellaneous Peition
04 Corrigendum to Review of True Up Order Passed on 21-02-2024 in Respect to APDOP Petition No. TP-01 of 2024
[DOWNLOAD]
TP-06 of 2024
05-04-2024
05/04/2024 Tariff Petition
03 Extension of Tariff Order Dated 25-10-2023
[DOWNLOAD]
TP-05 of 2024
22-03-2024
22/03/2024 Tariff Petition
01 Time of Day tariff order
[DOWNLOAD]
TP-04 of 2024
11-03-2024
11/03/2024 Tariff Petition
02 Review True Up Order for FY 2017-18, FY 2018-19, FY 2019-20, FY 2020-21, FY 2021-22 & FY 2022-23 Order dated 09-01-2024,For Department of Power - Government of Arunachal Pradesh
[DOWNLOAD]
TP-01 of 2024
21-02-2024
21/02/2024 Tariff Petition
01 True Up Order for FY 2017-18, FY 2018-19, FY 2019-20, FY 2020-21, FY 2021-22 & FY 2022-23 Order dated 09-01-2024,For Department of Power - Government of Arunachal Pradesh
[DOWNLOAD]
TP-02 of 2023
09/01/2024
09/01/2024 Tariff Petition